Delingha

From CSP.guru
Jump to: navigation, search



Basics

Status construction
Technology Tower
Capacity (MW) 270.0
Year operational 2017
Year of construction start 2016
City Delingha
Country China
Coordinates 37° 21' 26", 97° 16' 21"
DNI (kWh/m2 year) 1955


Financials

Storage capacity (hours) 3.5
Field size (m2)
Cooling
Expected generation (GWh/a) 628.4480
Load factor (%) 0.2657
Total cost
Specific investment cost (2015 USD)
Specific investment cost (2015 EUR)
Developer Brightsource
HCE manufacturer Brightsource
SCA manufacturer Brightsource
Financed through
Remuneration 1.15
Remuneration (2015 USD) 0.1830
Remuneration (2015 EUR) 0.1649
LCOE (5% WACC, 2015 USD)
LCOE (10% WACC, 2015 USD)
LCOE (5% WACC, 2015 EUR)
LCOE (10% WACC, 2015 EUR)
Other support
Owner State Grid of China
Support duration

Map

Loading map...

Links and sources

Enipedia ID
SolarPACES ID 4295

Data sources

http://www.nrel.gov/csp/solarpaces/project_detail.cfm/projectID=4295; http://www.brightsourceenergy.com/stuff/contentmgr/files/0/139e6c3f799d75a227a6c482257099f1/folder/delingha_fact_sheet_12_2_15.pdf; http://en.cspplaza.com/china-ndrc-formally-releases-official-notice-on-benchmark-feed-in-tariff-policy-of-csp-industry.html