Dhursar

From CSP.guru
Jump to: navigation, search



Basics

Status operating
Technology Fresnel
Capacity (MW) 125.0
Year operational 2014
Year of construction start
City Dhursar
Country India
Coordinates 26° 47' 9", 72° 0' 30"
DNI (kWh/m2 year) 1945


Financials

Storage capacity (hours) 0.0
Field size (m2)
Cooling Wet
Expected generation (GWh/a) 280
Load factor (%) 0.2557
Total cost 21000
Specific investment cost (2015 USD) 2754
Specific investment cost (2015 EUR) 2072
Developer Rajasthjan Sun Technique Energy, Areva
HCE manufacturer
SCA manufacturer Areva
Financed through
Remuneration 11.97 INR/kWh
Remuneration (2015 USD) 0.1963
Remuneration (2015 EUR) 0.1477
LCOE (5% WACC, 2015 USD) 0.1057
LCOE (10% WACC, 2015 USD) 0.1539
LCOE (5% WACC, 2015 EUR) 0.0795
LCOE (10% WACC, 2015 EUR) 0.1158
Other support Asian Development Bank $103 million; also from FMO (Dutch development bank)
Owner Reliance power
Support duration 25

Map

Loading map...

Links and sources

Enipedia ID
SolarPACES ID 272

Data sources

http://www.nrel.gov/csp/solarpaces/project_detail.cfm/projectID=272; http://www.cspworld.org/cspworldmap/rajasthan-sun-technique-dhursar; http://helioscsp.com/reliance-powers-100-mw-concentrated-solar-power-csp-project-at-dhursar-commences-generation/; http://social.csptoday.com/markets/what-does-areva’s-csp-exit-mean-india